WSPT Sign Excavator

Keeping Up With: The Westside Pump Track

June 10, 2021
Stay up to date with everything happening throughout the Westside Pumptrack renovation project!

With the Westside Pump Track project underway, we wanted to keep everyone up to date, in one place, throughout the duration of the project. It’ll also give you a little inside look into the process of completely renovating a pump track.

On a weekly basis, we’ll update this page so you’ll be able to find things like progress updates, pictures to go along with the updates, and any other noteworthy information relating to the Westside Pump Track. Expect about 8 weeks or so of updates.

Further, fundraising is still underway for the project as the goal has not been met. Support the local pump track by donating today.

Week 10: 8/8/21—Final Week

- The crew hung the signage up and did some prep for the grand opening party and now the track is officially complete!

D190 C4 BE DF27 430 F 96 CF 2 D608 C1 B79 A7
IMG 0092
IMG 0093
IMG 0174
IMG 0167

Week 9: 7/30/21

- Fencing installation is complete—all thanks to some serious customization work from the Trail Crew.

- Racing stripes were painted onto the track in the back half of the week. These lines will help with the visualization and safety of the track.

IMG 9574
IMG 9578
IMG 9579
IMG 9583
IMG 9617
IMG 9619
IMG 9571
IMG 9623
Image from i OS 9
IMG 9625
IMG 9621
Image from i OS 7
Image from i OS 5
Image from i OS 2
Image from i OS 1

Week 8: 7/25/21

- Starting ramp fencing installation underway.

- Drains cleaned up and completed.

- Some invasive plant removal from the outskirts of the track.

- Tops of retaining walls flattened and smoothed.

- Second slideshow shows photos from Friday's event with the Santa Cruz Bicycles' Sales Team. Photos courtesy of Lisette Cooper!

IMG 9439
64866846002 0 DF01 E74 E2 D5 4666 AA1 C 7164 D2 E10 EC3
64866844561 18 C81 CCD 8736 4560 A3 FC 4 EAAFA974 C31
IMG 9616
IMG 9514
IMG 9503
IMG 9504
IMG 9511
IMG 9507
IMG 9518
704 BE3 F3 A99 A 401 C 9436 8853891906 BD
997 D4536 4 CD3 4207 9 F0 D DE23214 CD4 AD
706 C845 B 8 DA6 45 A2 B905 665 A0 E116522
E1170 EC2 4 D37 4 CFF 845 D 8305 F73 A9 D67

Week 7: 7/17/21

- The track is paved!

- 3 days, 6 dump trucks of asphalt, ~36 hands and we have a paved Westside Pump Track.

- On Day 2 of paving, the entire SCMTS staff joined the Trail Crew to provide some extra hands.

Image from i OS 9
DSC04962
IMG 9242
IMG 9240
Image from i OS 13
IMG 9277
IMG 9286
IMG 9315
IMG 9325
IMG 9320
IMG 9385
IMG 9393

Week 6: 7/11/21

- Week 6 was dedicated to finishing the shaping of the track.

- The final berm was shaped.

- Volunteers helped with plate compacting and some drain work.

- A couple of minor feature alignment adjustments were made.

- The Summer Youth Trails Program joined forces with the Trail Crew this week—helping with fine-tuning, track sweeping, and more!

DSC04838 2
DSC04851
DSC04853
DSC04860
DSC04861
DSC04868 copy
IMG 9080 copy
IMG 9079 copy
DSC04869
Image from i OS 5
IMG 9194
WSPT Final Berm2

Week 5: 7/4/21

- Grading of the track is just about complete.

- We had a lot of base aggregate delivered this week. If you cruise by you'll notice the starting ramp is built up nice and high.

- Volunteers got busy this week at 2 separate events helping fine tune features.

WSPT Week5
WSPT Week5 2
WSPT Berm
WSPT Berm2
WSPT Starting Mound
WSPT Volunteers
WSPT Volunteers2
WSPT Volunteers3

Week 4: 6/27/21

- Laying of the base aggregate is well underway and consumed most of the crew's time during Week 4.

- Eastern end berms and southern side rollers have begun to be plate compacted.

IMG 8763
IMG 8761
IMG 8758
IMG 8757
Berm Compact2
Berm Compact
IMG 8677
DSC04515
DSC04513
DSC04509
DSC04474
DSC04469
DSC04444

Week 3: 6/18/21

  • Percolation basins set in.

  • Retaining walls set and complete.

  • Sub-grade carving of the track is underway.

  • Week 3 was our last week with the excavator as all major excavating is complete.

+ Fundraising for the project is still underway. Please consider donating today in order to keep the project on track. Through June 28th, all $5+ donations will automatically enter you in for a chance to win a FREE Trek kids' bike.
WSPT Percolation Basin
IMG 8480
IMG 8610
IMG 8609
IMG 8604
IMG 8602
IMG 8486
IMG 8606
IMG 8607
IMG 8485
IMG 8614
IMG 8601

Week 2: 6/11/21

  • Retaining wall placement underway

  • Retaining wall foundation compacted

  • Drainage pits completed

  • Rollers laid out on North side of the track


+ Tuesday, June 8th, we launched a fundraiser for the Westside Pump Track Project. Trek Bikes and Epicenter Cycling teamed up to donate 3 kids’ bikes for the fundraiser. All money raised goes directly to the Westside Pump Track as we inch closer to the goal. $125K out of $150K raised. Read more info here.

IMG 8409
IMG 8407
IMG 8405
IMG 8404
DSC04435
DSC04430
DSC04412
DSC04406 2
DSC04405
DSC04402
DSC04400
DSC04399

Week 1: 6/4/21

  • Prep work completed

  • Old track bulldoze

  • Drainage pits excavated

  • Erosion control set up

  • Retaining walls underway

  • Ground truthing complete

DSC04273
DSC04344
IMG 7993
DSC04375
IMG 8147 copy
DSC04358
DSC04253
DSC04264
DSC04265
DSC04270
DSC04277 1
DSC04342
DSC04362
DSC04337
DSC04341
DSC04326
DSC04349
DSC04382
DSC04367
DSC04391 1
DSC04390
DSC04354
DSC04281
DSC04365

Before Construction:

Pumptrack Fog Can
Pumptrack Fog Case
Pumptrack Fog pallets

^ SCMTS and Humble Sea collaboration beer: Westside Pump Track Fog. Proceeds from sales went straight to the project.

Original WSPT
Original WSPT2

^ Westside Pump Track before the bulldoze. Due for some attention.

WSPT Sponsor Banner 8 3 21
Share:
Become a member banner

Become a Member

Become a member of SCMTS! Join thousands of members who provide a reliable stream of support as we build and maintain sustainable trails throughout the Santa Cruz Mountains.